Clean Energy Action Dashboard
OverviewStart here: what this site covers Successful ProjectsStorage working in Westchester Model LawA common-sense code, not a ban Key ConsiderationsNine things boards should weigh Your Electric BillHow solar & storage cut costs Fire & SafetyThe evidence on BESS risk Size & SetbacksHow much room storage needs Risk in ContextHow battery risk compares Life CycleFrom factory to recycler

Size & Setbacks

From a single home battery to a utility project, drawn to scale, and the land that distance rules keep clear around it.

How much room does battery storage need?

Less than most people picture. One Tesla Megapack holds enough electricity to run about 200 New York homes for a day, and it fits in a single parking space. The bigger question for land is how far a town asks the equipment to sit from its neighbors.

How big is a battery?

Move the slider from a single home battery up to a large utility project. Each view is drawn to scale next to something familiar.

Seen from above

Tesla Megapack 2 XL · 3.9 MWh40 ft shipping containerParking space
  • Battery equipment, to scale
  • Familiar object, same scale

Stores

3.9 MWh

One Tesla Megapack 2 XL

Takes up

156 sq ft (28.9 × 5.4 ft)

About the size of

About one parking space, and shorter than a 40 ft shipping container

Could supply

About 209 average New York homes for a day

What is the rest of the site for?

Project filings list a number called the disturbance area: all the land cleared or graded during construction. On a large project the batteries are a small part of it. At the 240 MWh Long Island project, the battery units would cover about 0.2 of its 6.5 acres.

Staging for cranes,deliveries and materialsFenced battery yard20 ft fire lanesGrid connectionand transformersFirefighting waterStormwaterbasinAccess road6.5-acre work area
  • Battery units
  • Roads and fire lanes
  • Cleared for construction
  • Replanted

Illustrative layout, roughly to scale. The parts are the ones listed in the Aria project filing in East Fishkill. Real layouts vary by site.

During construction the whole work area is cleared or graded. Besides the batteries, it needs space for cranes, deliveries and materials.

Stays while the project runs

  • The fenced battery yard, with the spacing between units set by fire testing
  • Fire lanes wide enough for a fire truck, at least 20 feet under the fire code
  • The switchyard and transformers that connect to the grid
  • Water tanks for firefighting, stormwater basins, fencing and planted screening

Goes away after construction

  • Staging yards for cranes, deliveries and materials
  • Temporary roads and graded slopes
  • New York's construction stormwater permit requires every disturbed area to be stabilized, usually by replanting, before the permit can close

And at the end of its life, the decommissioning plan and bond that towns require pay to remove the equipment and restore the site. The Huntington project's 6.5 acres sit on an 11-acre industrial property, a precast concrete business at the time of its filing.

How much land does a setback take?

A setback is the minimum distance between the equipment and a property line or a nearby home. Pick a rule used in or near Westchester, or drag the slider, to see how much land it keeps clear around a 20 MWh site like Tarrytown's.

100 ft 100 ft
  • Battery site, 110 × 46 ft
  • Setback: no homes this close
  • Homes on quarter-acre lots

Setback

100 ft

Tarrytown, Ossining, Greenburgh

Land kept clear

1.55 acres

13 times the fenced site

About the same as

Room for about 6 homes on quarter-acre lots

About 1.2 football fields

That land can stay as lawn, woods or parking. What the distance really decides is which properties are big enough to host a project at all. Tarrytown's approved site sits on a 7.9-acre parcel.

What do the rules say today?

New York State

One fire code for every battery

The 2025 New York Fire Code took effect on December 31, 2025. Its battery rules are based on NFPA 855, the national standard, which spaces equipment according to large-scale fire tests and sets a default of 10 feet from property lines and buildings.

State model law

Towns set the distance

NYSERDA's model law, updated in its February 2026 guidebook, treats systems above 600 kWh as a larger class. It asks them to meet the same setbacks the zoning district already sets for buildings, with 10 feet cleared of brush.

Westchester

100 feet is common

Tarrytown (2025), the Town of Ossining (2021) and Greenburgh (2021) each require 100 feet. Tarrytown also keeps projects 200 feet from homes, and Greenburgh keeps its largest systems 500 feet from the nearest house. Several other towns have paused new projects while they write rules.

What is already built nearby?

Tarrytown

20 MWh

Approved by the Planning Board 4 to 0 in September 2025. About 110 × 46 ft inside the fence, on a 7.9-acre parcel, 200 ft from homes.

Hawthorne, Yorktown, Ossining

55.7 MWh

Three Tesla Megapack sites totaling 13.5 MW, completed in early 2025.

Huntington, Long Island

240 MWh

A 60 MW project using 6.5 acres of site work inside an 11.2-acre parcel.

How we know this

Sizes come from manufacturer datasheets: Tesla Powerwall 3 (2025), Tesla Megapack 2 XL (Rev 1.6, 2023: 8,800 × 1,650 mm), SolarEdge CSS-OD cabinet (April 2026: 1,100 × 930 mm, 97.3 kWh usable). Familiar objects: Maersk container specifications, ITF tennis rules, the NFL rulebook (360 × 160 ft), and a standard 9 × 18 ft parking space from the Town of Southeast code.

Homes for a day uses the average New York household: 571 kWh a month in 2024 (EIA), or about 18.8 kWh a day. A battery shifts power rather than making it, so this is a way to picture how much it holds.

Land kept clear is the fenced area pushed outward by the setback distance on every side, with rounded corners, which is what a minimum distance produces. A quarter-acre lot is 10,890 sq ft.

  • Tesla, Powerwall 3 and Megapack 2 XL datasheets. tesla.com
  • SolarEdge, CSS-OD battery cabinet datasheet, April 2026. solaredge.com
  • EIA, 2024 Average Monthly Bill, Residential (Table 5A). eia.gov
  • NY Department of State, 2025 code adoption notice. dos.ny.gov
  • NYSERDA, Battery Energy Storage System Guidebook, February 2026. nyserda.ny.gov
  • Village of Tarrytown code §305-68 (2025) and Planning Board minutes, 25 September 2025. ecode360.com
  • Town of Ossining code §200-31.4 (2021). ecode360.com · Town of Greenburgh, reported by the Scarsdale Inquirer, August 2021. scarsdalenews.com
  • Town of Warwick, proposed Local Law 5 of 2026 (hearing closed, not adopted). townofwarwickny.gov
  • Calibrant Energy and CS Energy, three Westchester projects, 2025. calibrantenergy.com
  • NYSERDA Bulk Storage Incentives, KCE-NY-21 public project summary. nyserda.ny.gov
Notes for reviewers
  • The Westchester draft code is still to come from Leo Wiegman. Its distance drops in as one more preset button.
  • The 10 ft fire code figure is NFPA 855 §4.4.3. We could not read the New York text of Fire Code §1207 to confirm New York kept it unchanged.
  • Greenburgh's numbers come from 2021 news coverage, and its code is being revised (County Planning, April 2026). The two published copies of Ossining's law disagree on height and brush clearance, not on the 100 ft setback.
  • Tarrytown's minutes describe the layout ambiguously, so the five-unit arrangement inside the fence is illustrative. The fence size is from the minutes.
  • The 240 MWh drawing is a square of the right area, and its unit count assumes Megapack 2 XL.
  • EIA's 2025 household figures are due in October 2026.